1.9 Science IPT
During January, the Science IPT Configuration Group delivered a revised ICD (version C) for the inner 172 antenna pads of the ALMA Configuration. This was considerably altered from the design approved by the JAO on 1 October but identical to that staked on the site during December and met a Level 2 Milestone for delivery of the inner configuration. Discussion with the Site and Antenna IPT suggested that allowance for pad position error and creep should increase the minimum antenna distance to 15.15m from 15m. Conway produced a further revised ICD (revision D) and submitted it for approval. Work continued on design of a long baseline part of the plan compatible with this new inner portion.
The primary activity of the Science IPT has continued to be production of the calibration plan for ALMA. A Level 3 Milestone for December 2002 produced a draft of calibration requirements document ready for reviews. This document updates Project Book Chapter 3.1 and review finished at the end of February 2003 (Level 2 Milestone). The Calibration Group discussed new reports for one of the two amplitude calibration devices being considered for ALMA, the subreflector dual load device, being tested at BIMA. A plan for initial testing of the other device, incorporating a semi-transparent vane, was discussed at a face-to-face meeting of mostly European Science IPT members in Leiden, including plans for testing the prototype on the 30m telescope during the Spring of 2003.
The Site Characterization Group led a survey of radio frequency interference levels at Chajnantor.
The Science IPT arranged the agenda, minutes and telecon for the ASAC on 4 December, 8 January and 5 Feb. Science IPT members from Europe gathered in Leiden 18-20 December; Butler represented the NA Science IPT members. Joint NA/EU Science Science IPT staff telecons were held 28 January and 11 February, and five NA Science IPT telecons were held. Calibration Group telecons 16 December and 7 February were also held.
Anticipated activity in the next bimonthly period
Milestones Level 3 and above; some modifications made as a result of Leiden meeting.
Milestone
|
Level
|
Scheduled Completion
|
I. B. 2. Configuration antenna motion logic
|
3
|
31 March 2003
|
I. B. 3. Revise configuration
|
3
|
31 March 2003
|
II. A. Calibration requirements Review
|
2
|
28 February 2003
|
II. B. 1. Atmospheric modeling software available
|
3
|
31 March 2003
|
II. B. 2. Draft specifications for calibration devices
|
3
|
31 March 2003
|
II.D.1 Draft WVR technical aspects (with FE IPT)
|
3
|
31 March 2003
|
III.A.1. Draft plan on attaining ACA goals
|
3
|
31 March 2003
|
There is one Level 3 completed in December 2002. A draft of the calibration requirements document has been produced for reviews. This is a modification of chapter 3 of the Project Book, complete with scientific examples for drivers. The Project Scientist issued a call to the ASAC during November to provide some examples for this exercise; they have been collected, discussed and disseminated. The calibration requirements document with science examples constitutes a Level 2 Milestone met 28 February 2003. A related Level 3 Milestone due in March 2003 will deliver draft specifications for calibration devices for reviews.
One Level 3 Milestone to be achieved in March will deliver to the project the ATM atmospheric modeling software being developed by Juan Ramon Pardo. This activity is in its final stages now; ATM has in fact been delivered to the European ADACE software project. This and other Level 3 and 4 Milestones lead toward the completion of the calibration strategy for ALMA, a Level 2 Milestone scheduled for September 2003.
In March 2003, a draft of the bandpass calibration plan will be presented, following publication and review of an ALMA Memo describing limitations of bandpass calibration using astronomical sources scheduled for February 2003. A presentation on this topic was given in Leiden and is available on ALMAEDM. Also in March, a draft of the phase calibration plan will be produced (Level 3). A further March milestone will be the production of the amplitude calibration plan, including total power calibration of ALMA. A further Level 3 milestone will review the SSR plan for all phase calibration techniques, for completion in March. Other items scheduled for March include a draft of the antenna location determination plan, a draft of the delay calibration plan, a draft of global antenna pointing plans, reference pointing plans, focus calibration plans, and a draft of an operational model for calibration, including ideas on sequence of moves and calibrations, dynamic scheduling, and number of antennas needed in 'calibration subarrays' .
Leading to the September 2004 report on WVR strategies (Level 2), a March 2003 Level 3 Milestone will present a draft document on technical aspects of the WVR, written in consultation with the Front End IPT.
By March 2003, the Science IPT will prepare a draft plan on how to achieve ACA goals (flux-recovered imaging at all ALMA bands).
1.9.1 ASAC
The Science IPT facilitated the ASAC Telecons held on December 2002, 8 January 2003 and 5 February 2003. It also supported discussions of the calibration examples, many contributed by ASAC members. In expectation of ASAC discussions on the topic, the Science IPT gathered arguments to provide scientific reasons for favoring an array consisting of antennas of like design.
2.9.2 Configuration
New data on the terrain at Chajnantor spurred revision of the array configuration to better
conform to the landforms on the site; this was revision C. The specification document
ALMA-90.02.00.00-001-D-SPE gives the pad numbers and positions for the first 172 pads
of baseline ALMA. The pads specified in this document will be used for configurations of
ALMA with maximum baselines out to 4.5km. An additional number of
Figure 1 A surveyor locates the position for on of the 172 antenna stations to be built on the site, as specified by the configuration group of the Science IPT.
pads will be needed for the larger (4.5 - 20 km) configurations. The positions and numbering of these additional pads will be presented in a future specifications document or revision to this document. The initial set of positions approached a form which may be confronted with site topology during the next month.
Y+ Configuration
Two options are still under consideration for the Y+ configuration. The first option considers the largest Y+ configuration as being separately optimized, with the intermediate steps offering somewhat poorer performance. Since the goal of this configuration is high resolution, this is the favored option at this time. A second option considers a series of semi-continuous moves (4 or 6 antennas at a time), with optimization of each step as a "stand-alone" configuration.
The two approaches have been debated at the last ASAC, and further work by M. Holdaway has quantified the expected differences. Operational considerations are also being taken into account.
However, simulations in which the largest configuration is complemented by short observations from the 4.5 km array (or a more compact one) may still be useful to define the optimal shape of the largest Y+ configuration.
Although the ALMA Compact Array proposed by Japan is not part of the baseline plan, the current site design provides (at no extra cost) two areas of 80x80 m located near the compact configurations which would suitable to host the ACA. The ACA could also be located further away from the centre of the ALMA compact array. Simulations to support a detailed ACA proposal were carried out at IRAM with substantial Japanese participation.
2.9.3Calibration
Butler organized and moderated a ALMA Calibration Group phone telecon 16 Dec. Discussion focussed on planning for the Leiden meeting which followed after a few days. Action items included review of calibration examples, semi-transparent vane test plan, distribution of the ASAC Report and work on polarization requirements. Examples were presented by Guilloteau at the Leiden meeting, as was a report on the test plan (presentations were place on ALMAEDM for general access. Minutes were published both of this meeting, and of the Leiden meeting, for general information. A second telecon on 7 February concentrated on progress toward Milestones, ALMA Memo reviews, calibration device performance tests, and proposals for absolute calibration from Welch and Guilloteau were introduced.
In ALMA Memo No. 402, Holdaway showed that offsets in the illumination of the dishes by the feeds would result in a phase gradient in voltage patterns, a serious problem for high dynamic range mosaicing. In a followup to that memo, Holdaway proposes a simple correction algorithm which can remove essentially the entire effect of the voltage pattern phase gradient. In the report, he explores how to measure the offsets and to apply corrections to the (u,v) coordinates.
Following a query from the Front End IPT, the Science IPT discussed the appropriate band for use with the ‘polarization widget’ lying above the dewar. After much discussion involving a large segment of the user community, a consensus was reached that the widget should be employed in conjunction with Band 7.
2.9.4 Site Characterization
Radford and Nyman proposed milestones for the site characterization group, which were discussed and merged into the Science IPT milestones.
A team from NRAO-Green Bank arrived at Chajnantor in December and carried out radio frequency interference tests for two weeks on the site. A report is in preparation. Specifications for emission from other projects to be located on the site (CBI, ASTE, APEX, and others) can be derived from this baseline survey.
Figure 2. Working with NRAO-Green Bank employees C. Beaudet and G. Watts, an initial radio frequency interference survey was made of Chajnantor during December 2002. This survey will enable specifications to be set for emission from other projects to be formulate.
An ALMA Memo is nearly ready to be submitted which discusses error sources on water vapor and delay as measured by the 183 Ghz radiometers on Chajnantor, based on work initiated by Guillermo Delgado.
1.8.5 Science Software Requirements
This group met face-to-face in Garching in December. Steve Myers and Jeff Mangum represented the Science IPT; much of the effort went to discussions of aips++. This being a group of the Software IPT, details should be sought in that report.
1.8.6 Imaging
Although it would be over reaching to call it imaging, the first of the ALMA prototype antennas successfully detected the Moon in January.
Activities centered on supporting definition of the ACA at IRAM. The ACA is under design in Japan. Imaging expertise was transferred from IRAM to JP. Interpretation of images requires some care. For example, from the fidelity definition, fidelity values will always be lower than the SNR. Here the SNR is defined as the Image peak intensity / theoretical noise, where the theoretical noise is deduced from the integration time and Tsys . The interpretation of the results is not obvious and was a focus of discussion.
Holdaway proposed a series of tests to ensure that prototype antennas may be capable of meeting the fast switching expectations. The Science IPT discussed these, making several suggestions. We feel confident that these tests will measure the antenna’s abilities to perform to expectations.
2.9.7 Organization
The organization and planning for the Science IPT during the construction phase of ALMA was reviewed and discussed with EU Science IPT members during the face-to-face meeting in Leiden. Sporadic telecons between the three project scientists continue, there is a monthly telecon for the whole Science IPT, and there is a weekly telecon of the NA Science Team.
2.9.8 Meetings, Outreach and Public Education
Science IPT Meetings during December-January 2002-2003, along with topics discussed, included:
Agenda for 3 December 2002 News-- FE/BE Reviews, Total Power on ALMA--how to achieve it, Calibration discussion, New correlator proposal.
Agenda for 17 December 2002 News-- New Org Chart, Milestone list, Proposal for Cerro Negro Instrumentation, Configuration, Calibration Meeting, Science IPT Meeting.
Agenda for 31 December 2002 News-- Leiden Calibration Meeting Review
Agenda for 14 January 2003 News-- FIRST LIGHT on VertexRSI Antenna, Configuration matters, Milestone list, Calibration Meeting Presentations.
Science IPT Agenda for 28 January 2003 Discussion of Leiden meeting, science examples for calibration, configuration, correlator upgrade.
Agenda for 4 February 2003 News-- Science Drivers for Single Antenna Design, Polarization
Widget Frequency, Level 2 Milestones Finalized, Calibration, Configuration.
Science IPT Agenda for 11 February 2003
Agenda for 26 February 2003 ALMA Board, Single Antenna Design Document, Band 7 for
Polarization Widget, WVR Items and Calibration, Configuration version 'D', Data Rates,
Illumination Offset Report, Dec-Jan NSF report for NA Sci IPT.
Calibration Group and ASAC Telecons were held as noted above.
Wootten represented ALMA at the NRAO booth at the American Astronomical Society meeting in Seattle Washington. At Caltech on other business, he discussed the state of ALMA informally with astronomers in the Caltech Submillimeter Observatory group, and with the OVRO group. Discussions included a meeting with postdocs and graduate students. In February he visited OVRO for discussions on practical issues and for observing.
2.9.9 Concerns
There is concern whether the Level 2 milestone of "Review of tests of calibration strategies on
prototype interferometer complete" can be met by December 2004. Although most elements of
the prototype interferometer will be in place at the ATF by early 2004, the prototype receivers
may not arrive until mid 2005 for testing later that year. The Science IPT believes that this must
be done earlier, if these calibration tests are to involve the actual ALMA receivers. Differences
between the evaluation receiver interfaces and those of the prototype receiver suggest that
substantial work would be required to implement the evaluation receivers for the prototype
interferometer. The project should construct a plan for component verification at the prototype
interferometer as soon as possible.
The IPT urges the project to publish minutes and action lists for the JAO/IPT and other meetings.
These are currently not disseminated.