2.9
Science IPT
During November, the Science IPT delivered the ICD for the inner
172 antenna pads of the ALMA Configuration.
This was considerably altered from the design approved by the JAO on 1
October and met a Level 2 Milestone for delivery of the iner
configuration. Work commenced on design
of a long baseline part of the plan compatible with this new inner portion,
A Level 3 Milestone for December 2002 will
produce a draft of requirements
document ready for reviews.
Final testing for
one of the two amplitude calibration devices being considered for ALMA, the subreflector dual load device, commenced
at BIMA. A plan for initial testing of the other device, incorporating a
semi-transparent vane, was discussed at a calibration telecon, at which
progress on the memo review process
(particularly that on the theory of the semitransparent vane system) and other
issues was also discussed.
The Science IPT arranged the agenda, minutes and telecon for the
ASAC on 6 November. Several Science IPT
staff telecons were held, regular Science IPT leaders
telecon continued, and a further joint NA/EU Science IPT telecon
was held. Guilloteau and Wootten
attended the ALMA Front-end specifications and
requirements meeting and the Back End LO design meeting in
Charlottesville. Further small changes in the list of Level 3 and 4 milestones
were made.
Anticipated activity in the next quarter
Milestones Level 3 and above
Milestone |
Level |
Scheduled Completion |
Who? |
I. B. 2. Configuration antenna motion logic |
3 |
March 2003 |
MH/JC/AO |
I. B. 3. Revise inner configuration |
3 |
March 2003 |
JC |
II. A. Calibration requirements Review |
2 |
February 2003 |
BB |
II. B. 1. Atmospheric modeling software available |
3 |
January 2003 [will be late?] |
JP |
II. B. 2. Draft specifications for calibration devices |
3 |
March 2003 |
JR/RH/JRP/JMP |
II. C. 1. Bandpass calibration plan draft |
3 |
March 2003 |
SG |
II. C. 2. Draft of phase calibration plan |
3 |
March 2003 |
?? |
II. C. 3. Draft of amplitude calibration plan, including Total
Power |
3 |
March 2003 |
?? |
II. C. 4. Review SSR plan for phase calibration |
3 |
March 2003 |
SM |
II. C. 5. Draft antenna location calibration plan |
3 |
March 2003 |
JC |
II. C. 6. Draft delay calibration plan |
3 |
March 2003 |
SG/AB |
II. C. 7. Draft antenna global pointing model plan |
3 |
March 2003 |
JM |
II. C. 8. Draft reference pointing/focus cal plan |
3 |
March 2003 |
JM/RL/PC |
II. C. 9. Draft calibration operational model |
3 |
March 2003 |
SM/MH |
II.D.1 Draft WVR technical aspects (with FE IPT) |
3 |
December 2002 |
RH/JR |
III.A.1. Draft plan on attaining ACA goals |
3 |
March 2003 |
?? [K-IM] |
There is one Level 3
scheduled for completion in December 2002. A draft of the calibration
requirements document will be produced for reviews. This is a modification of
chapter 3 of the Project Book, complete with scientific examples for drivers. The Project Scientist issued a call to the
ASAC during November to provide some examples for this exercise.
A Level 2 Milestone will
be reached during February 2003. This
will follow the results of the Level 3 Milestone above to include completion of
a review of calibration requirements with science examples complete. This includes: phase, amplitude, bandpass,
polarization, antenna location,
illumination offset, pointing, focus, delay, opacity, and decorrelation correction.
Two milestones during this quarter lead to the expected June
2003 Level 2 Milestone of the review of how calibration requirements trickle
down to instrumental specifications,
including special calibration devices.The first Level 3 Milestone to be
achieved in January will deliver to the
project the ATM atmospheric modeling software being developed by Juan Ramon
Pardo. This activity is in its final stages now.
A related Level 3 Milestons due in March 2003 will deliver draft
specifications for calibration devices for reviews. There will be separate specs for devices to be tested on the ATF
interferometer.
Other Level 3 and 4 Milestones lead toward the completion of the
calibration strategy for ALMA, a Level 2 Milestone scheduled for September
2003.
In March 2003, a draft of the bandpass calibration plan will be
presented, following publication and review of an ALMA Memo describing
limitations of bandpass calibration using astronomical sources scheduled for
February 2003. Also in March, a draft of the phase calibration plan will be
produced (Level 3). A further March milestone will be the production of the
amplitude calibration plan, including total power calibration of ALMA. A further Level 3 milestone will review the
SSR plan for all phase calibration techniques,
for completion in March.
Other items scheduled for March include a draft of the antenna location
determination plan, a draft of the delay calibration plan, a draft of global
antenna pointing plans, reference pointing plans, focus calibration plans, and
a draft of an operational model for
calibration, including ideas on sequence of moves and calibrations, dynamic
scheduling, and number of antennas needed in 'calibration subarrays' .
Leading to the September 2004 report on WVR strategies (Level
2), a December 2002 Level 3 Milestone will present a draft document on
technical aspects of the WVR, along with the Front End IPT.
By March 2003, the Science IPT will prepare a draft plan on how
to achieve ACA goals (flux-recovered imaging at all ALMA bands).
2.9.1
ASAC
The Science IPT facilitated the ASAC Telecons held on 6 November 2002 and 4 December 2002. In addition, the ASAC Report to the ACC was distributed to
Project and to the Public.
2.9.2 Configuration
New data on the terrain at Chajnantor spurred revision of the
array configuration to better conform to the landforms on the site.
Figure 1. The inner 172 pad positions are shown upon a
greyscale indicating elevation, ranging from 4800 to 5100m. The two yellow stars indicate the monuments
‘Master 0’ and ‘Master 71’ respectively.
The green dotted lineis the existing access road to the site from the
Jama highway. The red line follows the pipeline and the red crosses note the
crossing points along the pipeline.
The site characterization group
received the new aerial photographs and an autocad file of the site
contours from the Chilean company Aerotop.
However, no digital elevation model (DEM) was included in the materials
provided. Otarola and Holdaway worked
to turn the contour information into a DEM which could later be turned into a
mask for pad placement in the array optimization algorithms. Also, Angel and Holdaway studied the details
of the new DEM and determined it was of far superior quality to the old one,
but that the coordinates showed a systematic offset from the UTM frame. Communications with Aerotop indicated that
the coordinates were in fact not UTM and that the coordinate offset changes
slightly over the image. This resulted
in a clear understanding of site topography. Large offsets (>100 m) which
were coherent over 1 km scales, but which
varied over the 5 km x 5 km DEM, were found between the new and
old DEM. These offsets are attributed
to errors in the old DEM. As the
extended Y+ configuration has only the old DEM to guide its antenna placement,
pad misplacement (ie, onto the sides of gullys or other steep terrain) of the
order of 100 m is expected to be common, and this must be sorted out in the
surveying process.
Figure 2 The ALMA Compact Configuration. Contours are at 0.5m intervals.
Holdaway worked on finalizing the Y+ configuration, adjusting
the mask for terrain shadowing, inserting the new DEM mask in the center of the
old Y+ mask, and removing some hard-to-access regions. The Y+ configuration now has 42 antennas
moved out from Conway's largest configuration, the highest resolution
configuration is optimized
first, and the intermediate configurations are figured out after
the fact by moving 4 antennas each day.
More attention is being paid to the high resolution capabilities of the
array.
2.9.3 Calibration
Wootten, temporarily backing up Butler, on leave, organized and
moderated a ALMA Calibration Group phone telecon. Discussion focussed on the current planning for deployment of a
semitransparent vane at the IRAM 30m duriing the summer of 2003 and
tests which will be made there.
Reviews of Memos were discussed;
no review has yet been received of Memo No. 423 on the theory of the
semitransparent vane, so a call for reviews was urgently renewed. Wootten
provided Minutes of the meeting.
2.9.4 Site Characterization
Radford and Nyman held an organizational meeting and constructed
a proposed plan for construction phase activities.
Radford spent much of the month at the site upgrading, repairing
and testing equipment--this included replacement computers for the 225 GHz
tipper and the Site Testing Interferometer, installation of two new
surveillance cameras, reinstallation of the seismometer, restarting the
lightning detector, installing updated radiosonde software and diagnosing and
repairing submillimeter tipper at Sairecabur.
Radford also observed
with the SAO team at Sairecabur.
2.9.5
Science
Software Requirements
Myers worked on
responding to comments on his work with the Science Software Requirements group on audit requirements for
aips++. Mangum also works with this
group, as do the project scientists.
2.9.6
Imaging
Holdaway has added 1/f noise to the total power atmsopheric
simulations, which observe in both beam switched and on-the-fly modes.
Holdaway has made a preliminary study of a fast switching
decorrelation correction, in which the atmospheric phases measured on the
calibrator are used to estimate not only the mean phase correction to apply to
the target source visibilities, but also the degree of decorrelation to correct
the amplitudes by. This work indicated
that the correction worked well to correct the flux scale and recover the
correct peak flux, but that it increased the image noise level. More detailed studies will follow.
2.9.7 Organization
The organization and planning for the Science IPT during the
construction phase of ALMA was reviewed and discussed with Science IPT members
during the monthly telecon. Weekly
telecons between the three project scientists continue, and there is a monthly
telecon of the NA Science Team.
2.9.8 Meetings, Outreach and Public Education
Appendix A to the ASAC Report presented October 2002 was 'Report
of the ASAC Subcommittee on Site and Stringency' which included efforts of the
Science IPT Site Characterization Group, including undergraduate summer student
Selby Cull.
Science IPT Meetings during November, along with topics
discussed, included:
Science IPT Telecon 19 November 2002 News-- Science IPT
Organizational Chart, Milestones, Subgroup Reports, Upcoming Meetings
NA Science IPT Telecons
5 November 2002 News-- ACC Meeting, ASAC Meeting and Report,
FE/BE Reviews, Milestones v3.
26 November 2002 News-- FE/BE Reviews, Total Power on ALMA,
Calibration discussion
Report for
ALMA Calibration and Imaging
November 2002
NA
Progress Report
Overview
Milestones Achieved
Configuration
Calibration
Site Characterization
Science IPT ALMA Papers