Agenda
13:30 Introduction (Tan, Guilloteau):
-Review objectives
13:35 WVR in the ALMA system (Guilloteau):
-Function of the Water Vapour Radiometer in the ALMA system
Pathlength monitoring
Opacity sensor
Pending issues: anomalous refraction
-Relationship between ALMA Science requirements and WVR requirements (flow down)
-Operational implications
14:00 WVR programmatics (Tan, Guilloteau):
-Schedule
-Related WVR milestones for Science and FE IPTs
-Issues to be resolved: WVR prototype testing at ATF
-Atmospheric modeling
14:15 FE systems engineering (Harman, Rudolf):
-External WVR interfaces
-Internal WVR interfaces
14:30 Break
14:45 WVR status report (Richer, (Hills)):
-Comparison actual progress vs. planned
-Technical results
-Risks
16:15 Wrap up of meeting / action items (Tan, Guilloteau)
16:30 Adjourn
#
#