31 98705 9.380.98705 Report on phase correction analysis 2004-Jul-31 3 Late 2003-Jul-31 32 98707 9.380.98707 Report on accuracy of mesoscale atmosphere models 2004-Jul-30 3 Done 2003-Jul-31 33 98701 9.380.98701 Complete draft ICD between Science and Site 2004-Nov-30 3 Delay 2003-Nov-30 34 9818 9.380.9818 ICD between Science and Site Approved 2004-Apr-30 2 Done 2004-Jan-31 35 98221 9.380.98221 Draft of Design Reference Mission 2003-Oct-24 3 Done 2003-Oct-15 36 9820 9.380.9820 Calibration strategy submitted 2004-Feb-15 2 Done 2003-Sep-30 37 9822 9.380.9822 Design Reference Mission Submitted for approval 2003-Dec-10 3 Done 2003-Dec-31 38 98210 9.380.98210 Draft of operation model for calibration 2004-Mar-15 3 Done 2003-Mar-30 39 98214 9.380.98214 Revised antenna location determination plan 2004-Mar-15 3 Late 2003-Jun-30 40 98451 9.380.98451 Science verification plan for commissioning drafted 2004-Mar-03 3 Done 2003-Dec-31 41 98706 9.380.98706 Report on height of turbulent layer 2004-Mar-31 3 Late 2003-Dec-31 42 98301 9.380.98301 Draft plan for Early Science configurations 2004-Feb-29 3 Done 2004-Feb-29 43 98353 9.380.98353 Draft WVR software implementation plan 2004-Mar-30 3 Late 2004-Mar-30 44 98432 9.380.98432 Plan for interferometry tests on ATF complete 2004-Jul-31 3 Late 2004-Mar-31 45 9825 9.380.9825 Science aspects of operations plan complete 2004-Jul-31 2 Late 2003-Dec-31 46 9830 9.380.9830 Plan for early science configurations complete 2004-Jun-30 2 Done 2004-Jun-30 47 98401 9.380.98401 Prototype antenna motion tests complete 2004-Jun-30 3 Late 2004-Jun-30 48 98402 9.380.98402 Report on prototype antenna pointing in varying wind conditions 2004-Jun-30 3 Late 2004-Jun-30 49 98452 9.380.98452 Science verification draft for commissioning revised 2004-Jun-30 3 Late 2004-Jun-30 50 9835 9.380.9835 Report WVR strategy / implementation / operations 2004-Sep-30 2 2004-Sep-30 51 9840 9.380.9840 Review of tests of calibration strategies on prototype interferometer complete 2004-Dec-31 2 2004-Dec-31