35 9820 9.380.9820 Calibration strategy submitted 2003-Oct-31 2 Late 36 9822 9.380.9822 Design Reference Mission Submitted for approval 2003-Dec-31 3 Late 37 98210 9.380.98210 Draft of operation model for calibration 2003-Dec-31 3 Late 38 98214 9.380.98214 Revised antenna location determination plan 2003-Dec-31 3 Late 39 98451 9.380.98451 Science verification plan for commissioning drafted 2003-Dec-31 3 Late 40 98706 9.380.98706 Report on height of turbulent layer 2003-Dec-31 3 Late 41 98704 9.380.98704 Report on analysis of high precision hygrometer measurements. 2004-Jan-31 3 Delay 42 98301 9.380.98301 Draft plan for Early Science configurations 2004-Feb-29 3 43 98353 9.380.98353 Draft WVR software implementation plan 2004-Mar-30 3 44 98432 9.380.98432 Plan for interferometry tests on ATF complete 2004-Mar-31 3