ALMA Science IPT Telecon

Phone Meeting 2003-July-8


Connection Details


Old Business

The enhanced Agenda from last month's meeting is available, as are Notes.

- Action items from before the  previous meeting:
- Calibration
Action -- MH to consider Science losses in continuum images.  Please note ALMA Memo No. 466. Status: NYA.
ACTION -- AB: Standing wave, bandpass memos to be distributed for comment at next Science IPT meeting. Status: Standing wave memo available.
ACTION -- BB: Calibration reference document is not available outside the Science IPT.  This should be linked on ALMAEDM for reference purposes.
                      Status?

- SSR
Action -- Comments in to Richer by 20 May; revised data rate report due 16 June.

- Operations/Design Reference Mission working group (someone from WG)
Action -- Design reference mission needs to get off ground.         Stephane and Ewine circulated a plan of action.    This has commenced.

ACTION items from 10 June:

         ALL ACA feedback by July
             Declination coverage feedback due 24 June
         Data rate document 16 June. Richer
         Milestones: Y+ Configuration submitted 2003-June-30 Holdaway
                     Science Requirements submitted 2003-June-30 Butler
         Bandpass calibration document. Bacmann, Guilloteau
         Design Reference Science Plan - Project Scientists, E. van Dishoeck, lead
         Wobbler: Redesign?  Imaging group, Gueth, lead.

   - MILESTONES: all leaders of level 3 milestones with upcoming deadlines to report on status.  The Milestones, with project number, are available updated
for June 10.

New Business -- Agenda

Calendar

- Project news/updates (Wootten)

- ALMA Week followup (Al, Stephane)

Remaining items mentioned by other IPTs and groups requiring Science IPT followup.
(see Presentations)

Reports from Subgroups

   -1 Project Scientists (see above)

    -2 Calibration (Butler)

      - Update on semi-transparen t vane (Jesus)
      - Status calibration plan and milestones (Bryan)
      - standing wave, bandpass (Aurore, Stephane) 

     -3.Design Reference Science Plan (Ewine, Stephane)
              proposed plan of action outline circulated by Ewine
       
    -4. SSR (Lucas)

       - Data rate report: final version? (John R)
       - Report on SSR activities (Robert)

   -5. Configurations (Conway)
   -6 Imaging (Gueth)

         - report on activities (Frederic)
         - simulations gain stability (Mark)

    -7 Site (Nyman)

         - report on activities
                    RFI report due--is it available?  (Lars-Ake, Simon)
         - Site characterization database, stringency calculator (Holdaway)
         - Ancillary Devices latest draft (Hills, Richer)

-8 Others (outreach, ...)
        New PR IPT to be formed.
     -9  Any Other Matters Arising  

Upcoming Meetings

JUL 13-26, 2003 Twenty-Fifth General Assembly of the IAU Abstracts due long ago.

JUL 27/25, 2003 IAU Symposium (271): Star Formation at High Angular Resolution, Sydney, Australia. Tyler Bourke is a co-chair of the scientific organizing committee. Good opportunity to show ALMA capabilities.

SEP 22-26, 2003 4th Cologne-Bonn-Zermatt-Symposium on The Dense Interstellar Medium in Galaxies