ALMA
Science Advisory Committee
19-20
March 2002
Mitaka,
Japan
Draft
Minutes
Participants:
R. Bachiller, G. Blake, R. Booth, L. Bronfman, R. Brown, Y.
Chikada,
T. Cornwell, P. Cox, C. Cunningham, N. Evans, Y. Fukui, P. Gray,
S.
Guilloteau, T. Hasegawa, M. Ishiguro, R. Kawabe, R. Kurz, J. Mangum, D.
Mardones,
H. Matsuo, N. Nakai, M. Rafal, J. Richer, S. Sakamoto, P.
Schilke,
Y. Sekimoto, P. Shaver, K. Tatematsu, M. Tsuboi, E. van Dishoeck,
M.
Walmsley, W. Wild, A. Wootten, S. Yamamoto, M. Yun
G.
Blake welcomed all participants to this face-to-face meeting of the
ASAC.
The proposed agenda and plan for writing the report were accepted.
1. Project Update
M.
Rafal summarized the project status. In the U.S., $12.5 million are
already
available for construction in FY 2002, and NSB approval is expected
shortly
on the complete construction project. For FY 2003 the President's
budget
requests $30 million for continued construction funds. An inflation
projection
of 3.6% p.a. is assumed. In Europe, construction approval is
expected
in July, and the proposal foresees a slower ramp-up in funding
than
in the U.S. This difference in the funding profiles is one of the
issues
the AEC is currently dealing with. M. Rafal mentioned major upcoming
events,
including the ACC meeting on 18-20 April (major items Phase 2 plans
and
the International Project Office) and ALMA week on 23-27 April at which
there
will be over 100 participants and both plenary and parallel sessions.
R.
Kurz gave an overview of the baseline project scope and schedule. The
first
production antenna should be on the site in the 4th quarter of 2005.
By
the end of 2006 there will be seven antennas, and science commissioning
will
begin. In the 4th quarter of 2007 interim science operations should
begin.
The overall schedule has been extended by one year, to 2011. R.
Booth
asked when the central project office will be staffed, and R. Kurz
replied
that the applications are coming out now.
2. Current Project Status in Japan
M.
Ishiguro summarized the current status of the project in Japan. The ASTE
10-meter
antenna has been completed and moved to the 4800-meter Pampa la
Bola
site. It is currently being equipped with its SIS receivers and
spectrometer,
and the infrastructure is being developed. The 12-meter
prototype
has been approved, as has a new building at Mitaka, which will
include
the SIS fabrication facility. The 12-meter prototype is due to be
delivered
at Socorro in April 2003. It will have the same specs as the
European
and U.S. prototypes, and will weigh 80 tons. Negotiations with
MEXT
and the Ministry of Finance are continuing for participation in the
global
ALMA project by FY 2004 or earlier.
3. Project Status in Chile
R.
Brown and L. Bronfman gave an overview of the project status in Chile. A
"direct
concession" to a Chilean entity is being considered, which may be
managed
by a "concessional committee". Aspects of site protection were
discussed.
The proposed location of the OSF at 2800 meters altitude was
described.
It will not be too far from San Pedro, and staff will have the
option
of living in San Pedro rather than at the OSF.
4. Prototype Antennae Update
M.
Rafal described the progress with the U.S. prototype. Delivery is
expected
in July. Concerning the European prototype, R. Kurz said the
amended
contract had been signed on 18 December 2001, with what is now an
Alcatel/Costamasagna/EIE
consortium. The final design will accommodate the
Media
Laurio panels; these have a surface accuracy of 6.6 microns,
consistent
with an overall 20 micron rms surface accuracy. M. Ishiguro said
that
the Japanese 12m prototype will have a surface accuracy of 20 microns
rms
and pointing accuracy of 0.6 arcsec. Delivery is due in Socorro in
April
2003.
5. Revised Testing Program in Socorro
J.
Mangum summarized plans for testing the prototype antennas. All three
evaluations
should be completed by 1 January 2004. They will be done by an
Antenna
Evaluation Group (AEG), and an Antenna
Evaluation Working Group
(AEWG)
will be comprised of an extra pool of members. No prototype
frontends
will be used for the evaluation of the prototype antennas. He
said
that interferometer and spectroscopic measurements may not be used to
evaluation
the prototype antennas; interferometry can improve the results,
but
is not essential. The interferometer would later be used to test the
software
and system. The decision on the contractor is due in October 2004,
and
then it will be about one year to the first production antenna. The
goal
is one final design, although there could be several contractors.
6. Prototype Receivers and LO
W.
Wild reviewed progress on the prototype receivers. He reported on work
at
IRAM on the optics and alignment at IRAM (completed), and work on the
windows
and calibration (three types are being tested). The cryostat
development
work at RAL received the go-ahead at the September 2001
meeting.
He reported on work underway on band 7 (IRAM DSB, OSO 2SB) and
band
9 (NOVA/SRON), the IF amplifier development (SRON, Yebes, Chalmers),
and
the water vapour radiometer (MRAO, OSO). C. Cunningham reported on the
progress
in North America on bands 3 and 6. R. Booth and S. Guilloteau
stressed
the emphasis on sideband separation up to 350 Ghz. S. Guilloteau
said
that 4-8 Ghz sideband separation may be adequate (as opposed to 4-12
Ghz).
E. van Dishoeck stressed the importance
of the stability of the
receivers.
To her question about the first production receivers, W. Wild
said
that there were too few people available for timely completion. N.
Evans
suggested that a complete review of the production issue may be
needed
by the next ASAC meeting.
7. IF Subsystem and Baseline Correlator
P.
Gray, the new N. American system engineer, gave a status report on the
backend
and correlator. Major milestones in the schedule are completion of
the
backend (12/03), the correlator prototype (10/03), and the final
quadrant
(10/07).
8. Calibration, WVR System
A.
Wootten reported that a Calibration Group has been formed, led by the
Project
Scientists (A. Wootten and S. Guilloteau). R. Lucas is the liaison
between
the SSR and the Calibration Group. R. Booth suggested that liaison
with
the people on site (L.-A. Nyman and others) was also desirable . A
prototype
of the semi-transparent vane system (IRAM) will go to the
prototype
antenna. The dual load calibration system (BIMA) is now being
built
at NRAO. There is no report yet on the standard gain horn (BIMA).
Concerning
phase calibration, a 183 GHz WVR is
being tested on the SMA,
and
a 22 Ghz radiometer at OVRO. IRMA will be installed at Chajnantor in
mid-2002.
There are many PDR actions.
The
issue of bandpass calibration was discussed by S. Guilloteau - the
options
of the noise source through the subreflector, and the
semi-transparent
vane system. The latter will be prototyped at IRAM and
tested
on the test interferometer. Regarding atmospheric transmission
modeling,
there is now a model good to 2% over the range 0-2 Thz, and an
implementation
technique is required.
9. Options for Proposal Review Committees
N.
Evans said that there was a preference to refer to a "Proposal Review
Committee"
rather than a "TAC". Two alternative concepts were considered in
detail:
subject-based and partner-based PRCs. P. Shaver asked in what
language
proposals would be written in Japan; T. Hasegawa replied that they
would
be in English if there were more (Asian) partners with Japan. R.
Bachiller
asked whether it would be necessary to account for individual
member
countries within the ALMA partners (eg. Europe). P. Shaver commented
that
this is not done, for example, by ESO. The concept of stringency was
discussed,
and whether high stringency time should count the same as low
stringency
time. The dynamic scheduler was also discussed; it could include
partner
parity over a long enough time scale. S. Guilloteau commented that
legacy
programmes, like the HDF, must be done. It was realized that the
report
could avoid making a specific recommendation for a particular type
of
PRC, as all could be made to work; the important point is that the
policy
requirements are satisfied in the most efficient way. There was
further
discussion on the principles and use case, and general agreement on
the
principles. The point was made that the simulator will do most of the
technical
assessment. The question of how to account for staff observing
time
remains an issue. Generally it was agreed that time should be counted
in
accordance with the partner membership of the PI of a proposal, but
there
was the additional question of whether co-Is should be counted also.
N.
Evans summarized the outcome of the discussion and recommendations.
Recommendations
to the ACC on partner parity will be: decouple parity from
the
PRC method (the dynamic scheduler helps here); consider
stringency-weighted
time; and allow different ways to count the time (coIs
may
be included). Recommendations to the project: work with the ASAC to
define
stringency more precisely; and assess the statistics of stringency
at
the site (considering such long-term effects as El Nino). Y. Fukui
commented
that more time should be spent on legacy projects, and P. Shaver
added
that there would be strong support for this from the wider community.
10. Overview on RSC Core Functionalities
The
core functionalities were generally agreed to comprise user support
(assistance
with observation preparation, data reduction, and archival
research),
feedback on performance, and hosting the archive or a copy of
the
archive. Questions concerned the overlap with Virtual Observatory for
archival
research, whether the archive should be a physical copy or just a
link,
and the relation to the SOC. Y. Fukui felt that software development
should
be considered a core function. Whether or not that is the case, it
was
agreed that software development has to be part of ALMA, and has to be
funded.
Concerning the SOC, P. Cox said its responsibilities were not yet
defined.
L. Bronfman said it would be useful to Chile
to add core
functions
to the SOC. E. van Dishoeck commented that the SOC should be
responsible
for the pipeline and quality control, and users get data
products
directly from the SOC/OSC/Observatory. N. Evans said that an RSC
is not
a SOC. P. Cox commented that the RSCs provide feedback to the SOC.
11.
European Presentation on RSCs
P.
Cox gave a summary of discussions
concerning the European RSC. It would
provide
day-to-day support. For development work, it would be a strong
central
node in a European network, and external funds would be required
for
non-core activities.
12. Japanese Presentation on RSCs
Y.
Fukui said that in Japan there already was a central body (NAOJ); the
core
functionalities would be similar, but should also include software
development.
Other possible activities of the RSC were suggested: updating
(including
the archive), promoting science with ALMA (eg in summer
schools,
hosting meetings). 10 FTEs were considered a reasonable maximum.
L.
Bronfman said that in Chile the core functions could be carried out in
Santiago
(or at the OSC); added functionality would be to transmit science
and
education to the country. D. Mardones commented that RSCs may not
really
be needed - except for non-radio astronomers, those working
predominantly
in other (eg. optical/IR) wavebands.
13. North American Survey Results
N.
Evans summarized discussion in North
America. There would be just one RSC for the N. American partner countries.
Added functions would include software support
and
outreach. Providing financial support was very important; software
development
had a lower priority. The location should be near an air hub,
more
convenient than the present NRAO locations. It should be operated by
NRAO.
The FTEs are estimated in the range 10-40, at 50/50
functional/scientific
work. Astronomers should be able to
access any of
the
RSCs. T. Hasegawa asked where all the upgrades for ALMA would be done.
R.
Brown replied that there is a a draft operations plan; the Director
directs
the observatory and its local and partner-supplied staff; the
partners
are the executives, and they provide the upgrades, both hardware
and
software.
14. AIPS++ testing report
S.
Guilloteau gave a report on the testing of AIPS++ for off-line
processing
of ALMA data. The goals are (1) to see if it can be suitably
adapted,
(2) to know how long the learning curve is, and (3) to do an end
to
end experiment on actual mm spectral data. The status so far is that the
exchange
format has been received and accepted, the data set has been
selected,
and the data set results have been transferred from IRAM to the
AIPS++
team. The AIPS++ adaptation has been found to be OK. There is no
answer
yet on the end to end experiment on actual mm data, but there are no
obvious
show-stoppers. If the tests are
successful, AIPS++ can be used as
a
basis for ALMA data reduction.
15. NRAO Data Management Plans, including
the end-to-end product
T.
Cornwell described the data management plans at NRAO. The effort started
in
May 2000, and will result in a large improvement in data services for
the
user. It includes the management of AIPS++, and the management of
computer
services and policy. It will streamline observer access, and
greatly
improve the data products and the archive. It is an "end to end
(e2e)
project", involving 65 FTE-years over about five years. It is new
territory
for NRAO, and will use a "spiral development model". There are
many
similarities to plans for ALMA. The connectivity was stressed between
NRAO
and the National Virtual Observatory. There will be a pipeline and
archive
facility document. T. Cornwell commented that an important
consideration
is that experts are location dependent - they cannot easily
be
moved, so inter-site collaboration should be encouraged.
16. Baseline receiver bands production
report, Europe and N. America
In
introducing this topic, W. Wild commented that ALMA will need 512-1152
SIS
mixers, compared with 200 currently operating in the world today. He
gave
a summary of issues for mass production. He emphasized that it is
important
to learn from space programmes, and to test receivers on the
Chajnanaor
site. The objective is to have a receiver run for one year
without
problems. C. Cunningham mentioned as examples the specific cases of
bands
6 and 9 production. There are many sources for the various
components
for each receiver. These would come to receiver integration sites, one of which
would be at Tucson. There would be automated receiver test sets for each
receiver.
"Repair" will involve on-site replacement by a "hot" unit.
The
faulty
unit will be taken to the OSC, so at least some aspects of the
receiver
test set must be there.
17. Receiver production report, Japan
Y.
Sekimoto gave an overview of the receiver production plan in Japan. He
mentioned
the quality control issues, the major technical issues, the test
equipment,
and the pre-production engineering model including on-site
evaluation
with ASTE. He described a new facility that will be built at
NAOJ
for ALMA, which will include a clean room, assembly room, etc.
G.
Blake asked all three speakers when we need critical items in order to
get
the receivers on time. The answer was this year. J. Mangum stressed the
need
to have the receivers on site on time. R. Brown said that the antennas
and
receivers will be done in synch. S. Yamamoto commented that
interferometry
should be done as soon as possible. S. Guilloteau said that
it
will be important to have at least one receiver with every cartridge for
tests.
18. Results of Configuration CDR, Imaging
Performance
A. Wootten reviewed the Configuration CDR
that took place on 24-25 January
2002.
Highlights included an elegant design theory developed by Boone (and
used
now for the Allen array), sidelobe optimization techniques by Kogan,
the
Delannay u-v optimization elaborated by Webster, and the hybrid u-v and
beam
optimization elaborated by Conway. Ampngst the action items:
appointment
of a leader; appointment of a consulting engineer; high
resolution
imagery and maps; a report and update at the forthcoming "ALMA
Week";
a site development PDR in September; and a complete configuration
design
by January 2003. Various options are still under study for the
compact
configuration, and the intermediate and large configurations. A
possible
Y-shaped configuration for 8-9 km baselines is under
consideration,
which includes antennas along the OSF road. L. Bronfman said
that
it was important to know what "exclusive areas" are needed for ALMA
(outside
areas may be shared with other possible projects).
19. Towards a 3-way ALMA
R.
Brown reviewed the evolution of plans for the project since last
October.
At that time the ACC had requested details for the baseline
project.
There is now a simplified WBS, which is far better than before.
The
costs are under control, and it shows the scope of the baseline project
and
the overall schedule: 4Q 2002 - agreement signed with Chilean
government;
3Q 3002 - RfP released for production antennas; 4Q 2004 -
antenna
contract(s) awarded; 4Q 2005 - first production antenna at the OSF;
4Q
2006 - start of science commissioning operations; 4Q 2007 - start of
interim
science operations; 2011 - all antennas on site. Japanese entry
into
the project will provide the enhancements. M. Ishiguro said that, in
order
to have a 3-way project in 2004, a budget proposal was required
before
August 2003. A draft agreement is needed, specifying what Japan
should
provide. At the ALG meeting on 18 March 2002 it was stressed that
close
collaboration between the three partners is necessary on many
aspects:
overall project planning, antenna evaluation, 2G correlator
coordination,
and frontend/LO photonics development coordination. S.
Guilloteau
commented that the configuration already allows Japanese
participation.
The priority list is clear, but M. Ishiguru expressed the
view
that if the ACA is a necessary Japanese contribution, it should be
pushed
to the highest frequencies. T. Hasegawa said that he would
eventually
like the ASAC to make a recommendation/endorsement for a model
for
Japanese participation. Y. Fukui said that there should be a lot of
interaction
with the project and with ASAC before June 2003. T. Hasegawa
outlined
a schedule involving working group meetings in April, June,
September,
and December.
20. Preparation of Reports
Following
meetings of the sub-groups, the group leaders presented outlines
of
their draft reports for comments and discussion.
The
report sections are as follows:
Project
status, management: from minutes
Site
issues, configuration: Booth, Bronfman, Sakamoto
ACA
simulations, science: Cox, Crutcher, Hasegawa, Welch
Correlator:
Bachiller, Scoville, Yamamoto
Operations:
Evans, Fukui, Wilson
Software: Benz, Gurwell, Tatematsu
Calibration,
WVR: Matsuo, Richer, Wilson
Polarization:
Crutcher
Receivers: Blake, van Dishoeck, Nakai
Antennae,
test interferometer: Fukui, Walmsley,
Welch
ASTE,
APEX: Kawabe/Yamamoto, Schilke
21.
Election of new Vice-Chairperson
G.
Blake announced that C. Wilson will be the next North American
vice-chairperson
of the ASAC.
22.
Next Teleconference and Meeting
The
next teleconference is scheduled for Wednesday April 3, at the usual
time.
The
next face-to-face meeting is tentatively scheduled for September 2002
in
Socorro.