Activity ID Activity Desc. OD Start Finish Expected Finish COMMENT BY IPT 1.09.09.2 Milestones 3537d 27Nov02A 2-Aug-12 1.09.09.2.15 Configuration Models 907d 27Nov02A 21-May-05 ? See IPT reports. I do not recognize 21-May-05 This must have been the date for the inner config now done and passed to Holdaway for outer stations Estimate that done July 6. 1.09.09.2.15.6 Re-baseline Plan 90d 21Feb05A 21-May-05 No idea what this means for Early Science ES Array Configuration has Array Configuration been done for more than a year. CCB told me not to bother theproject with it. 1.09.09.2.15.7 Re-baseline Plan 0 21-May-05 21-May-05 As above; it is done. for Early Science Array Configuration Complete 1.09.09.2.16 Interferometery Tests 655d 31Jul04A 16-May-06 We need an interferometer at the ATFfirst. Depends on SE&I. 1.09.09.2.18.4 Review of tests of 0 29-May-05 29-May-05 Ditto. calibration strategies on ATF interferometer 1.09.09.2.20 External ICDs 197d 01Apr05A 2-Jan-06 1.09.09.2.20.1 ICD 47 SCIE -Weather 30d 01Apr05A 2-Jan-06 2-Jan-06 Brian and I decided this Stat. - COMP SW Draft was not really needed. 1.09.09.2.20.3 ICD 57 SCIE -Weather 30d 01Apr05A 31-May-05 31-May-05 Draft in almaedm could Stat. - Site Meteorology be done in 1 day when - Draft I get time.