Responsible:
Lambeth

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Modification Required (Draft) Lambeth http://ed 386

Procedures

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Signed http://ed 386

Procedures

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Not Started Lambeth http://ed 386

Procedures

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Review (by Effland) Required Effland http://ed 386

Procedures

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Review (Technical) Required Lambeth http://ed 386

Procedures

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Review (by Effland) Required Effland http://ed 386

Procedures

Band 6 Cartridge Cold IF Phase Matched Cable Test FEND-40.02.06.09- Modification Required (Draft) Lambeth http://ed 386

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Modification Required (Draft) Lambeth http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Review (by Effland) Required Effland http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Review (by Effland) Required Effland http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Review (by Effland) Required Effland http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Review (by Effland) Required Lambeth http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Not Started Lambeth http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Modification Required (Draft) Lambeth http://ed 388

Procedures

Band 6 Cartridge Semi-Rigid Cable Thermal Cycling FEND-40.02.06.09- Signed http://ed 388

Procedures

Band 6 Cartridge Warm IF Amplifier Chain Test FEND-40.02.06.13- Checking Required Lambeth http://ed 449

Procedure
__________________________________________________________________________________________________________________
Report:'rptResponsible' (Ver:2007-06-13 11:29:07) Printed: 2007-06-27 8:53:31 AM Page 31 of 47
Datasource: 'qryResponsible' (Ver: 2007-06-11 10:27:12) \\cvfiler.nrao.edu\cv-cdl-
__________________________________________________________________________________________________________________
First Previous Next Last