Title
ALMA #
Status
Waiting On Link Rec. #
__________________________________________________________________________________________________________________

Responsible:
Dan Koller

Band 6 OMT Specifications FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 394

Band 6 OMT Block RFQ FEND-40.02.06.03- Modification Required (Draft) Effland http://ed 444

Band 6 OMT Block RFQ FEND-40.02.06.03- Signatures Pending Effland http://ed 444

Band 6 OMT Block RFQ FEND-40.02.06.03- Not Started Koller http://ed 444

Band 6 OMT Block RFQ FEND-40.02.06.03- Signed http://ed 444

Band 6 OMT Block RFQ FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 444

Band 6 OMT Block RFQ FEND-40.02.06.03- Signatures Pending Effland http://ed 444

Band 6 OMT Block RFQ FEND-40.02.06.03- Signatures Pending Saini http://ed 444

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Signed http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Modification Required (Draft) Koller http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Review (Technical) Required Koller http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Not Started Koller http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Modification Required (Draft) Koller http://ed 445

Band 6 OMT Mechanical Inspection Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 445

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 382

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Not Started Koller http://ed 382

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Signed http://ed 382

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Modification Required (Draft) Koller http://ed 382

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 382

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Not Started Koller http://ed 382

Band 6 OMT Assembly Procedures FEND-40.02.06.03- Modification Required (Draft) Koller http://ed 382

Band 6 OMT Test Procedures FEND-40.02.06.03- Signatures Pending Saini http://ed 447

Band 6 OMT Test Procedures FEND-40.02.06.03- Review (by Effland) Required Effland http://ed 447
__________________________________________________________________________________________________________________
Report:'rptResponsible' (Ver:2007-06-13 11:29:07) Printed: 2007-06-27 8:47:39 AM Page 8 of 47
Datasource: 'qryResponsible' (Ver: 2007-06-11 10:27:12) \\cvfiler.nrao.edu\cv-cdl-
__________________________________________________________________________________________________________________
First Previous Next Last