•Unofficial top-level results, based on exit
debriefing by panel to
IPT Management and M. Rafal
–Official report and IPT response by mid-April
•Well prepared PDR; at or ahead of where similar projects
have been at this
stage
•The ALMA Project needs to develop an understanding of operations, and the Computing IPT needs to fold this in
to their planning and
priorities. This might result in reprioritization
of SSR requirements
•ALMA project needs to define clearly
the steps necessary for getting to, and implementing, Interim Operations and the consequent requirements
for computing support
•