Next: Future Issues
Up: Report of the ALMA
Previous: Antennas and Total Power
Water-Vapor Radiometry
Accurate phase calibration is a critical requirement for ALMA, and the
baseline design of ALMA uses a 183 GHz receiver (mounted slightly
off-axis from the astronomical beam) to measure a strong atmospheric
water line. Under various assumptions about the atmospheric pressure
and temperature, and the location of the turbulence, the electrical
path above each antenna can be derived. Richard Hills and John Richer
contributed a report outlining the status of the 183 GHz
systems currently in place (Appendix E),
and a series of suggestions for the requirements of a second
generation system. Christine Wilson presented a report by
David Naylor (Appendix F)
on an alternative strategy that uses a 20m
photometer to measure water vapor fluctuations in the infrared.
These reports were discussed in detail. The specific recommendations
of the ASAC are:
- 1.
- The water vapor radiometers are central to the scientific
success of ALMA, and the project should ensure that their development is
adequately resourced and integrated with all aspects of the ALMA
system.
- 2.
- The project should design and test preferably two (identical)
prototype/pre-production 183 GHz radiometers as part of the Phase 1
project. These should be tested on reasonable
astronomical sites when completed. The possibility of putting them on
the 12-m prototype antennas at the VLA site during the test
interferometer work is highly attractive, and the feasibility of this
option should be investigated.
- 3.
- The project should adopt a specification for the WVR system as
follows: it should correct the atmospheric path above each antenna to
an accuracy of 10(1+wv)m on a timescale of 1 second, over a
period of 5 minutes and allowing for a change in zenith angle of 1
degree; wv is the precipitable water vapor in mm.
- 4.
- Although it is not possible to put very firm design constraints on
the optics, the project should adopt as the specification that the
maximum permissible offset between radiometer and astronomical beams
be 10, and (if possible) smaller for the higher frequency
channels.
- 5.
- The project should check that the above specifications are
sensible and adequate. In particular, the short timescale behavior
of the atmosphere should be quantified to ensure that correction of
phase on 1 second timescales is rapid enough.
- 6.
- There are scientific and productivity gains
to be made by correcting the wavefront tilt across each antenna (the
so-called ``anomalous'' refraction). This effect most strongly
compromises mosaic observations, and those at high
frequencies. However, given that there are large periods of time when
this effect will not be a major problem, the ASAC does not recommend
adopting such a system as the baseline design at present. Further
study of the loss of observing time this effect produces should be
made, and this recommendation should be reassessed at future meetings.
- 7.
- The baseline design for the water vapor radiometer remains a
183GHz system.
The alternative Canadian solution using 20m radiometers
should be examined further, probably by the Canadians themselves, and
further reports on progress should be brought to the ASAC.
In particular, the correlation of
the 20m and 183GHz systems should be examined on the JCMT.
The main theoretical problems of the 20m technique that need to
be investigated are its ability to sample the correct patch of
atmosphere; its performance in differing cloud conditions; and the
accuracy of the path estimation as a function of pressure, temperature,
and water vapor distribution.
- 8.
- The baseline design should use a cooled 183 GHz radiometer.
Whether to cool or not is, strictly speaking, an engineering problem;
there was
some feeling that although not absolutely required to achieve the
required sensitivity, the benefits of cooling in terms of stability
and noise probably outweigh the costs.
- 9.
- The project should examine the role of the system water vapor
radiometers in the following:
a) the amplitude calibration system, through their
estimates of the atmospheric opacity above each antenna; and b) in
single-dish mode observing, where they could be used to estimate the
atmospheric emission. The scientific benefits of these techniques,
and the extra requirements they place on the system, should be
investigated.
- 10.
- The project should accelerate its work on understanding the
different atmospheric models used by the WVR systems to predict path
errors from water line measurements.
- 11.
- The location of the WVR is an engineering problem, and the
solution likely
depends on the degree of cooling required, and the final optical
design adopted. There appear to be no show-stopping problems with
locating it either in the same Dewar as the astronomical receivers, or
in its own cryostat. The optimum engineering solution should be
investigated. The ASAC does note that the simultaneous operation at
183 GHz and Band 1 receivers is not a scientific requirement, so
it is straightforward to locate these systems in the same Dewar if
that makes sense.
Next: Future Issues
Up: Report of the ALMA
Previous: Antennas and Total Power
Al Wootten
2000-04-04