As an aid to planning for 2002 and beyond, here are the key project schedule milestones for the 3-way project that we discussed in Paris. The most visible milestone, delivery of the first production antenna to Chile, occurs one year later in the 3-way project than it did for the 2-way project plan.
ALMA Project Schedule (3-way project)
2002 April | Delivery of first prototype antenna to VLA test site |
2003 April | Delivery of third prototype antenna to VLA test site |
2004 February | Select 'best' prototype antenna; Initiate contract negotiation |
2004 October | Sign production antenna contract |
2005 October | Delivery of the first production antenna to Chile |
2005 December 31 | 3 production antennas in Chile |
2006 December 31 | 15 production antennas in Chile |
2007 April (approx) | Initial science users--"shared risk" science observations |
2010 December 31 | Construction complete |
--------
Payne reports that the edge taper issue was discussed in the Receiver Meeting.
Are we happy with this? Is the taper which is best for interferometry also going to be what we want for total power mode?
--------
Configurations, ACA, Correlator and of course, the ASAC Face-to-Face meeting in Chile.
--------
--------
Travel
Oh, always
------