MMA Imaging and Calibration Group

Agenda for meeting Tuesday, 31 Jul 2001 at 4pm EDT.

Date: 31 Jul 2001

Time: 4:00 pm EDT (2:00 pm Socorro, 1:00 pm Tucson)

Phone: (434)296-7082 (CV SoundStation Premier Conference phone).

Past minutes, etc on MMA Imaging and Calibration Division Page

Minutes

--------

News. -Wootten

News from my point of view.

As an aid to planning for 2002 and beyond, here are the key project schedule milestones for the 3-way project that we discussed in Paris. The most visible milestone, delivery of the first production antenna to Chile, occurs one year later in the 3-way project than it did for the 2-way project plan.





ALMA Project Schedule (3-way project)



2002 April Delivery of first prototype antenna to VLA test site
2003 April Delivery of third prototype antenna to VLA test site
2004 February Select 'best' prototype antenna; Initiate contract negotiation
2004 October Sign production antenna contract
2005 October Delivery of the first production antenna to Chile
2005 December 31 3 production antennas in Chile
2006 December 31 15 production antennas in Chile
2007 April (approx) Initial science users--"shared risk" science observations
2010 December 31 Construction complete


--------

Meetings Last Week-Wootten

Payne reports that the edge taper issue was discussed in the Receiver Meeting.

Are we happy with this? Is the taper which is best for interferometry also going to be what we want for total power mode?

--------

Upcoming Meetings - Wootten

Configurations, ACA, Correlator and of course, the ASAC Face-to-Face meeting in Chile.

--------

ACA Report -- Holdaway, Wootten

--------

Calibration PDR -- Wootten

Wootten's draft report is available. 

Travel

Oh, always

------