| Tasks Updated from Last Week |
Description | AssignedTo | Date | Who | | Notes |
| Updated |
DateEntered | | Date Completed |
| Amplifier Test System |
| Repackage Components | Lambeth | Thu Nov-15 | Lambeth | Estimated completion date changed from 2007-11-01 to 2007-11-16.I have received all the |
| http://www.cv.nrao.e | Mon Oct-29 | 9:53 | | crucial parts and I am completing the point-to-point wiring to finish the new fixed bias |
| Cartridge Assembly (Production) |
| Fabricate Waveguide Windows | Horner | Thu Nov-15 | horner | All three windows have been Leak tested and pressure tested. Passed both test. |
| http://www.cv.nrao.e | Fri Sep-07 | 10:23 |
| Cartridge Test (Production) |
| Cartridge 003 | Schmitt | Wed Nov-14 | Schmitt | Completed phase stability testing, temperature stability of the test lab still plagues this |
| http://www.cv.nrao.e | Thu Sep-06 | 13:59 | | measurement with some measurements meeting specifications while others come close. |
| Cooled IF Amps |
| Order next Batch of 24 Preamps from ACC | Morgan | Thu Nov-15 | Morgan | First 5 units received 11/15/2007. Production order will be placed after these units have been |
| http://www.cv.nrao.e | Wed Jul-18 | 8:38 | | RF tested. |
| Get more MAP100 Devices from Goddard | Lambeth | Thu Nov-15 | Lambeth | The tape on the new wafer section seems OK, but flexes a bit more than the tape on our old |
| http://www.cv.nrao.e | Fri Oct-12 | 9:28 | | section. This seems to have caused some of the devices to fracture along the various flex lines, |
| Resolve pocket location and standoff bonding issues | Morgan/Lambeth | Mon Nov-12 | Lambeth | Duplicate... Disregard |
| http://www.cv.nrao.e | Mon Nov-12 | Mon Nov-12 | 11:40 |
| Resolve pocket location and standoff bonding issues | Lambeth | Mon Nov-12 | Lambeth | High priority flag set.From: Michael R. Lambeth [mailto:mlambeth@nrao.edu] |
| http://www.cv.nrao.e | Mon Nov-12 | 11:38 | | Sent: Monday, November 12, 2007 11:30 AM |
| Additional working bottom lids for preamp | Lambeth | Thu Nov-15 | Lambeth |
| http://www.cv.nrao.e | Thu Nov-15 | Thu Nov-15 | 14:09 |
| Preamps 133-137 | Lambeth | Thu Nov-15 | Lambeth | High priority flag set.Upgrading to high priority |
| http://www.cv.nrao.e | Thu Nov-15 | 9:08 |
| Miscellaneous Tasks |
| General Tasks | Groves | Thu Nov-15 | Groves | 1) deburred 10 preamp bodies with lids and submitted them to the plating lab. |
| http://www.cv.nrao.e | Wed Nov-07 | 16:25 | | 2) In the process of acquiring an RMA # to return Pan's vacuum pump out for repair. The |
| General Tasks | Horner | Thu Nov-15 | horner | Estimated completion date changed from 2007-11-10 to 2007-11-17.5th set of heat straps |
| http://www.cv.nrao.e | Wed Nov-07 | 13:33 | | 80% completed |
| General Tasks | Johnson | Thu Nov-15 | fjohnson | Prepared several sets of chips for M Lambeth |
| http://www.cv.nrao.e | Wed Nov-07 | 11:15 |
| Friday, November 16, 2007 | Page 1 of 3 |