New ALMA Logo

ALMA Science IPT Telecon

Phone Meeting 2004-August-24


Connection Details


Old Business

The enhanced Agenda from last month's meeting is available.  Science IPT notes from last month's telecon. Last Meeting Action items    
Action items from Last month's Science telecon:

ACTION: John will work on the antenna location plan        Still in process, draft available (see below)

SE telecon.  ACTION: [Wootten]- what is the required IDR for a single image.  Bring this up in the science telecon. Proposed Text.
                   ACTION: Science IPT, [Laing]- produce short memo on origin of spec on differential gain stability. [N.B. ALMA Tech Requirement No. 264 Differential gain stability between channels of a polarization pair 5e-4 at 300 sec TBC allocation to FE and BE are each 0.707 of this value 320 23]  See Holdaway's study.  ALMA System Technical
Specifications have been approved by the CCB.  See item No. 264 and comments on page 10.

ALMA Week:  [Wootten]Provide detailed values on solar filter to FEND by 30 April .  Comments on these values?
                        [Laing] Develop a requirement for stitching together the BEND 2 GHz sections for overlap.      In process; see comments at CR79 linked below, which lead to a further linked document on this subject by Comoretto, Butler and others.
                        [Conway, Laing] Choose antenna stations where first antennas will be located for first fringes.  4-30-04   [See CSV document]   
                        [with SE]  Decide when antennas are handed over to Commissioning (after 1st light or 1st fringes?) 6-01-04  [See CSV document]   

             MILESTONES: all leaders of level 3 milestones with upcoming deadlines to report on status.  The Milestones, with project number, are available updated for last month.

New Business -- Agenda

 ALMA Calendar 

LAMA Memo Series  has  inhabitants!

Project news/updates (Wootten and Wilson)
     * JAO Positions PS job description... (Wootten)  
     * CCB APPROVED  ALMA System Technical Requirements     
     *  ALMA Board Response to ASAC Report

Reports from Subgroups

   -1 Project Scientists (see also above)  See ALMA Science IPT wiki page.
       * News from Japan (Kawabe)
       * New ASAC Charges (Wootten)
       * ARCs.  Paul vanden Bout has begun to form the North American ALMA Science Center.
       * NRAO Communications  Newsletter
       * ESO proto-communique
     
  -2. Configurations (Conway)   -3 Calibration (Wootten)  Mangum will be at a procurement meeting.   See ALMA Science IPT wiki page.  A Calibration page is listed under that.
      - The Requirements and Specifications August 03 Version (Wootten)
      -  Draft Bandpass Calibration Memo. from Bacmann and Guilloteau (3 of 3 reviews, favorable,  received; final version near completion)
                    - Very drafty Calibration plan.
      - Plan for further tests of amplitude calibration devices:   Progress? (Martin-Pintado)
      - Please see the report from Berkeley on the absolute calibration via gain horn experiment.

     -4.Design Reference Science Plan (Hogerheijde )
      - Calibration attributes of projects

    -5 Imaging (Stirling, Holdaway)  
        -  A second release of the atmospheric simulation package will be available.  See the readme description.

   -6. SSR (Lucas?)
       -  Minutes of this month's meeting--only subsystem scientist reports.

    -7 Site (Radford, Nyman)
         -   ICDs

   -8 Operations, Science Commissioning and Verification (Laing)

       -  ALMA Commissioning and Science VerificationSkip to reply button for entry 1. Group -- Laing, Emerson, Chandler, Lucas, Mangum, Shepherd, Wilson, Wootten, Saito, Morita, Kawabe
    -9  Any Other Matters Arising
             

Upcoming Meetings

    Upcoming Meetings - Wootten

Cores, Disks, Jets & Outflows in Low & High Mass Star Forming Environments: Observations, Theory and Simulations  July 12-16, 2004  Banff, Alberta, Canada

ESO ALMA COMMUNITY DAY 2004 September 24 Garching Germany

The Cool Universe: Observing Cosmic Beginnings   2004 October 4-8  Universidad Tecnica Federico Santa Maria, Valparaiso, Chile

New Windows on Star Formation in the Cosmos  2004 October 11-13 University of Maryland, College Park, Maryland

Dusty and Molecular Universe  27-29 October 2004, Paris
Astrochemistry throughout the Universe: Recent Successes and Current Challenges 2005 August 29 - September 2;  Asilomar, CaliforniaNew!

Protostars and Planets V  24 - 28 October 2005  Hilton Waikoloa Village, The Big Island, Hawaii

URSI General Assembly  23-29 October 2005; New Delhi, India;  "Mm/submm Techniques and Science" session 25-26 Oct.